  • Nonlinear Seismic Evaluations of Castaic Intake Towers and Access Bridge. Report prepared for the California Department of Water Respources, Sacramento, California, September 15, 2017.
  • Nonlinear Static and Seismic Evaluations - Log Cabin Dam. Report prepared for Yuba County Water Agency, Marysville, California, February 1, 2017.
  • Nonlinear Static and Seismic Evaluations - Our House Dam. Report prepared for Yuba County Water Agency, Marysville, California, February 1, 2017.
  • Nonlinear Static and Seismic Evaluations - New Bullards Bar Dam. Report prepared for Yuba County Water Agency, Marysville, California, June 20, 2016.
  • Nonlinear Seismic Evaluation of Perris Dam Outlet Tower. Report prepared for the California Department of Water Respources, Sacramento, California, September 12, 2015.
  • Static and Seismic Evaluations of Swan Lake Dam for Current and Raised Water levels. Report prepared for the Southeast Alaska Power Agency, Ketchikan, Alaska, February 9, 2015.
  • Linear and Nonlinear Seismic Evaluations - Donnells Arch Dam. Report prepared for Tri-Dam Project, Strawberry, Tuolumne County, California, May 5, 2014.
  • Guidelines for Determination and Use of Reservoir Bottom Reflection Coefficient. Research report to the US Army Corps of Engineers, Waterways Experiment Station, Vicksburg, Mississippi, November 2003
  • Finite-Element Stability Analyses of Claytor Dam. Report to American Electric Power, Columbus, Ohio, June 2003
  • Technical Review and Analysis of Design Documentation Report (DDR), Folsom Dam Outlet Modifications Project, American River Watershed. Report to the US Army Corps of Engineers, Headquarters, Washington D.C., May 2003
  • Finite-Element Structural Analyses of Hemlock Dam. Report to the US Army Corps of Engineers, Portland District, February 2003
  • Linear and Nonlinear Finite-element Analyses of Claytor Dam. Report to American Electric Power, Columbus, Ohio, September 2002
  • Independent Technical Review, Folsom Mini-Raise Project, American River Watershed, Long-Term Study, California. Report to the US Army Corps of Engineers, Headquarters, Washington D.C., November 2002
  • Time History Dynamic Analysis of Smithland Dam. Report to Smithland Hydroelectric Partner, Ltd., Bethesda, Maryland, June 2002
  • Static Stability of Smith Mountain Dam. Report to American Electric Power, Columbus, Ohio, September 2001
  • Time History Seismic Evaluation of Walters Dam. Report to ARCADIS Geraphty & Miller, Chattanooga, Tennessee, February 2000
  • Measurement and Prediction of Dam-Water-Foundation Interaction at Longyangxia Dam. Final report to the US National Science Foundation on Research Conducted Under the US-China Protocol for Scientific and Technical Cooperation in Earthquake Studies, November 1999
  • Static and Dynamic Re-analyses of Karapiro Dam. Report to Mighty River Power (formerly Electric Company of New Zealand), Hamilton, New Zealand, May 1997
  • Evaluation of Theoretical, Seismically Caused, Vertical Contraction Joint Opening for Brush Creek and Slab Creek Dams. Report to Sacramento Municipal Utility District, Sacramento, California, January 1996
  • Sensitivity Earthquake Analysis of Brush Creek Dam. Report to Sacramento Municipal Utility District, Sacramento, California, April 1994
  • Sensitivity Earthquake Analysis of Slab Creek Dam. Report to Sacramento Municipal Utility District, Sacramento, California, April 1994
  • Experimental Study of Dongjiang Dam for Dam-Water-Foundation Interaction. Final report to the US National Science Foundation on Research Conducted Under the US-China Protocol for Scientific and Technical Cooperation in Earthquake Studies, July 1993
  • Nonlinear Earthquake Analysis of Portugues Dam. Report to the US Army Corps of Engineers, Jacksonville District, June 1991

 